• Baltic Power, Poland's first offshore wind project, completed the installation of all 76 turbines across the 1.1 GW facility in the Baltic Sea.
  • The project is advancing through commissioning and is on track for commercial operations in 2026, with overall costs aligned with original expectations.
  • Once operational, Baltic Power is expected to generate approximately 4 terawatt-hours of electricity annually, providing enough clean energy to power more than 1.5 million Polish households.

TORONTO, Oct. 07, 2026 (GLOBE NEWSWIRE) -- Northland Power Inc. ("Northland" or the "Company") (TSX: NPI) today announced the completion of turbine installation at Baltic Power, the 1.1 GW offshore wind project in Poland jointly owned by Northland and ORLEN. All 76 turbines are now installed, with over one-third currently generating power. The project is advancing through commissioning and is on track for commercial operations in 2026, with costs aligned with original expectations. Baltic Power achieved first power in July 2026, delivering the first electricity ever generated from offshore wind to Poland’s national grid.

Globenewswire